Large Solar PV Arrays Likely Not Feasible in Dalton

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
DALTON, Mass. — Large multi-megawatt solar panel photovoltaic array projects are likely not feasible in the near future. 
 
Green Committee member Todd Logan updated the committee last week on his efforts to obtain data to inform the possibility of developing large PV arrays on town properties.
 
The town's Climate Action Plan consultant, Blue Strike Environmental, requested information on what it should focus on when developing the Climate Action Plan. 
 
The company needed data on the town's energy generation capacity to determine the type of feasible projects for the town. 
 
Eversource provided the Green Committee with a distributed generation hosting pre-application report, which it will provide to Blue Strike.
 
The latest information provided granular data, including the substation transformer rating, the substation's circuit voltage and name, the phase available near the site, and the distance from the phase service if it's a single phase. 
 
It also includes standards for the interconnection of distributed generation, including information on aggregate connected facilities that have not yet been interconnected, the interconnecting customer's network types and nearby feeders, and potential system constraints that may impact the proposed facility, among other things. 
 
The Eversource data informs which more tangible and feasible projects Blue Strike Environmental should focus on. 
 
The Eversource representative also informed Logan that due to a group of very large grid-connected energy generation projects already in the queue, a study has to be conducted to see the impact on the Eversouce circuit that serves Dalton. 
 
The Eversource representative indicated that the grid infrastructure would likely need to be upgraded to accommodate these projects. 
 
Until the study is complete, circuit 18C BERKSHIRE's hosting capacity will be unclear. This will make it unclear what type of projects the town is able to do in the future, Logan said. 
 
If the upgrades are needed, each energy project will have to contribute to the cost of the upgrades, he said. 
 
The Eversource representative could not give Logan many details about the project, such as the timeframe and scope. 
 
In other news: 
 
The installation of electric vehicle (EV) charging stations at the Community Recreation Association has been delayed, committee member Antonio Pagliarulo said. 
 
Dave Callahan of Universal EV Charging Station, who is overseeing the project, is ready to install the stations, but Eversource is delayed, Pagliarulo said. 
 
It is unclear when the project will be completed but they hope to have it done in August.
 
Committee members suggested that the town decide which composting station model to use for its transfer station, either the Egremont Transfer Station's model or Williamstown compost's model.
 
They also would like a Green Committee representative to be part of the transfer station study. 

Tags: green committee,   solar array,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Lanesborough Picks Information Panel for Public Safety Proposal

By Brittany PolitoiBerkshires Staff

LANESBOROUGH, Mass. — The town has a public safety building proposal to present to taxpayers, and now, an informational committee will help move the process forward.

On Monday, the Select Board voted to form a public safety building informational outreach committee and re-appointed four members: Dean Clement, Daniel MacWhinnie, Mark Siegars, and Lisa Dachinger.

"The Public Safety Building Committee has done their job. Now we need, hopefully with some of those same bodies, to form a new committee of some type and move forward," Select Board member Timothy Sorrell explained.

Earlier this month, the town officials voted to advance a $7.3 million combined police/emergency medical services facility to town meeting, discarding the option for a $6.5 million separate build.  The same design, then priced at $5.9 million, was shot down in 2023.

"There is the option to go to what could be a debt exclusion, which requires a two-thirds majority at either a special town meeting or an annual town meeting, and that can be followed by inclusion in a ballot," Town Administrator Gina Dario said.

Siegars advised that if the question goes to a ballot first with a fixed project budget, that amount can't be changed for a subsequent special town meeting vote.

"In our discussions, there are committee members who are willing to stay on if you wanted to continue the committee or appoint to new one, who have volunteered to be involved with any public information sessions to try to answer the questions with the idea that that they would also explore further and work with Gina and town counsel on specifically what the question should be for a special town meeting, and if, if warranted a subsequent ballot vote," he reported.

Chairman Michael Murphy echoed the former committees' arguments that the town can't explore grants and financing until it has approved an amount.

View Full Story

More Pittsfield Stories