Dalton Planning Board Works to Update Special Permit Fees

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
DALTON, Mass. — The Planning Board is navigating how to update its special permit fees to bring them up to date with the current costs of services. 
 
During the board meeting last week, Town Planner Janko Tomasic said the cost of completing the services is higher than what it costs to take action on the application.
 
The current application fee charged by the Board of Appeals and the Planning Board is $375. 
 
This fee is intended to cover the cost of labor, time, materials, postage for the certified abutters list for abutter notification, postage for the certified mail for the notice of the decision, and two Berkshire Eagle legal advertisements for the public hearing.
 
"According to the data, the base cost for a permit application is barely enough to cover the cost of the application process," according to Tomasic's special-permit costs breakdown. 
 
Based on the last six permits, the least expensive permit is $414 to complete because of the increase in cost for the steps in the permit process.   
 
The flat certified mail fee for eight letters is $69.52, which covers the cost of certified mail to abutting towns, the applicant, and notice of the decision to the applicant
 
The abutters list is $25, and two legal advertisements in The Berkshire Eagle is $268.40.
 
Board members asked if there was another paper they could use with a cheaper legal advertisement fee. 
 
The Berkshire Eagle is the only place to legally advertise as public notices are required by law to be posted in a print newspaper. The town can not just do online advertisements, Tomasic said. 
 
"We can't unfortunately advertise anywhere else. So, I'm exploring those options. I think, right now, we're legally tied to The Berkshire Eagle. We can't just do online advertisements. I'm not quite sure why. I didn't get a straight answer on that, but I spoke to [Town Manager Tom Hutcheson,] and he said for right now, we have to do The Berkshire Eagle,"
 
"So when there are other chances to switch where we can legally advertise. I think that would be a good thing to do. But as of right now, can't we're kind of stuck with The Berkshire Eagle.' 
 
These base expenses leave only $12.19 for the postage for the Notice of Public Hearing letters. 
 
The town is legally required to send a Notice of Public Hearing letter to all abutters within 300 feet of the property.
 
Over the years, materials and services have been rising in cost, including the fees for The Eagle advertisements, postage, and the two different fees for an abutters list. It is unclear when the town last updated its fees.
 
"The general public pays $50 for a certified abutters list, while a special permit or variance applicant only pays $25," the cost-breakdown sheet states.
 
"The current fee the Town of Dalton has for its applications is not reflective of the actual cost of the materials, work, and time needed to go through the process."
 
If the town does not address this, it will become a problem for the town budget, Tomasic said. 
 
He proposed two potential solutions: a tiered system in which the number of abutters is separated into ranges, and there is a set fee for each range or a set fee with an additional cost of $8.69 per abutter. 
 
In a follow-up, Tomasic said he prefers the second option because it is more accurate to the cost of services. 
 
When looking at what other towns are doing, they have a flat fee and an additional charge for the cost of postage for abutter notification, he told the Planning Board. 
 
The board directed Tomasic to draft an updated special permit application with this new fee system for the board to review at its next meeting. 

Tags: fees,   Planning Board,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Lanesborough Picks Information Panel for Public Safety Proposal

By Brittany PolitoiBerkshires Staff

LANESBOROUGH, Mass. — The town has a public safety building proposal to present to taxpayers, and now, an informational committee will help move the process forward.

On Monday, the Select Board voted to form a public safety building informational outreach committee and re-appointed four members: Dean Clement, Daniel MacWhinnie, Mark Siegars, and Lisa Dachinger.

"The Public Safety Building Committee has done their job. Now we need, hopefully with some of those same bodies, to form a new committee of some type and move forward," Select Board member Timothy Sorrell explained.

Earlier this month, the town officials voted to advance a $7.3 million combined police/emergency medical services facility to town meeting, discarding the option for a $6.5 million separate build.  The same design, then priced at $5.9 million, was shot down in 2023.

"There is the option to go to what could be a debt exclusion, which requires a two-thirds majority at either a special town meeting or an annual town meeting, and that can be followed by inclusion in a ballot," Town Administrator Gina Dario said.

Siegars advised that if the question goes to a ballot first with a fixed project budget, that amount can't be changed for a subsequent special town meeting vote.

"In our discussions, there are committee members who are willing to stay on if you wanted to continue the committee or appoint to new one, who have volunteered to be involved with any public information sessions to try to answer the questions with the idea that that they would also explore further and work with Gina and town counsel on specifically what the question should be for a special town meeting, and if, if warranted a subsequent ballot vote," he reported.

Chairman Michael Murphy echoed the former committees' arguments that the town can't explore grants and financing until it has approved an amount.